PROCESS
Remediation earthworks were performed by asbestos removal contractors Focus Demolition under the direction of the principal contractor West Force Construction. Initially remedial works involved the removal of filled ground in the western half of the site; this was however extended to include the eastern half of the site at the request of the Water Corporation.
In all, the entire 1.7 ha area of the site including 0.3 m beyond the site boundary was removed down to undisturbed ground.
Limestone base was applied to the ground surface to minimise contact with the impacted ground surface prior to removal by excavator and to prevent cross contamination between contaminated and clean soils.
A total of 14,789 tonnes of soil was disposed off-site to landfill at completion of remediation Clean quarry sand was imported to site and used to backfill and compact excavations performed across the entire site.
Following remediation, Lyon Environmental performed soil validation collecting in excess of 250 samples across the sitesite.
All validation samples were tested for ACM (asbestos containing material) by sieving with fines sent for laboratory analysis for any fibres.
All final validation samples were compliant with the remediation criteria of no detectable ACM fragments or asbestos fines/fibrous asbestos (AF/FA).
Air monitoring was undertaken daily during the remediation works.